Green Choice Program Procurement Timeline

Updated: September 10, 2026

The table below provides the expected timeline of the Green Choice Program Procurement. Power Advisory reserves the right to adjust the schedule as needed.

EventDate
Posting of Draft RFP & PPAJune 2, 2026
WebinarJune 18, 2026
Issue Final RFPSeptember 10, 2026
Deadline for Proponent RegistrationSeptember 17, 2026
 Deadline for Feasibility Study Submission to IESO Nova Scotia September 30, 2026
Deadline for submitting questions and commentsOctober 8, 2026
Deadline for Issuing Addenda October 29, 2026
Proposal Submission Deadline January 14, 2027
Target Date for Notice of PPA Awards May 6, 2027